If you own an unapproved flat, the first step is a private inspection by a building certifier or surveyor, before anyone contacts council: it tells you what has to change and roughly what it will cost. Then decide between legalising, returning the building to its approved use, or removing it.

What our analysis shows

Our calculations, data as of 23 October 2026

  • At Sydney's median one-bedroom detached rent, a $15,000 compliance bill is recovered in about 42 weeks of rent after agent fees and tax. A $60,000 rebuild of slab, ceiling or fire wall takes about 3.2 years.
  • A 2025 NSW buyer was given a rental appraisal for a new house's studio flat by the selling agent, then told by council after settlement that it could not be rented until about $15,000 of work was done. A rental appraisal is not evidence of approval.
  • Legalising is a different process in each state. NSW and WA issue certificates for existing unauthorised work; Victoria does not issue retrospective building permits. A complying development certificate cannot approve work that has already been built.

What unapproved means

A granny flat is approved when it has planning approval for use as a dwelling (a CDC, development approval or permit, depending on the state) and building approval, with a final inspection or occupation certificate. A flat can be partly approved: a studio approved as a home office, a garage approved as a garage, a workshop with plumbing approved but not for anyone to live in. Using it as a self-contained dwelling then needs approval for that use as well.

The risks

  • Council orders. To stop the use, make it comply, or demolish. Councils mostly act on complaints, often from neighbours.
  • Insurance. Insurers may refuse a claim connected with a structure used in a way it was not approved for, especially if a tenant is hurt or a fire starts in it.
  • Safety. The approval process checks damp-proofing, fire separation, smoke alarms, ceiling height, wiring and drainage. Without it you do not know.
  • Lending and sale. Valuers usually give an unapproved flat no value, lenders do not count its rent, and the contract for sale must disclose it in most states.

Legalising by state

StateRoute for existing work
New South WalesBuilding information certificate from council for the existing work, plus approval for its use as a secondary dwelling (CDC is not available for work already done)
VictoriaNo retrospective building permit; a building surveyor may issue a permit for rectification work, and a planning permit may be needed for the use
QueenslandRetrospective building approval through a building certifier; linings or cladding may have to be removed for inspection, and an owner-builder permit cannot be issued retrospectively
Western AustraliaBuilding approval certificate from the local government for unauthorised work

Whichever route applies, the building has to meet the code for a dwelling, which means reports and often opening walls. Owners in our forum sample listed the usual items: damp-proofing the slab, a fire-rated wall where the flat adjoins another building, termite protection, a structural engineer's certificate for the frame and a minimum 2.4 m ceiling in habitable rooms. Start with a building certifier or surveyor's inspection, not with an application, so you know what has to change.

Is it worth legalising?

Weeks of rent needed to recover the bill, after agent fees and tax at 30%:

Legalisation billSydney 1-bed detached ($550)Western Sydney 1-bed detached ($450)Brisbane 1-bed ($590)
$10,00028 wks34 wks26 wks
$15,00042 wks52 wks39 wks
$30,00084 wks103 wks79 wks
$60,000169 wks206 wks157 wks

Paperwork, minor fixes and a certificate in the $10,000–15,000 range pay for themselves within a year of rent. If the slab, ceiling height or boundary setback cannot comply, the bill approaches the cost of a new flat, and demolishing and building new can be the better choice; compare with our cost calculator.

Buying a property with one

  • Ask the agent and the vendor in writing which approvals exist for the flat, and check council records yourself.
  • Have the building inspection cover the flat as a dwelling: damp, wiring, smoke alarms, fire separation, drainage.
  • Price the property as if the flat may have to be returned to its approved use, and treat any rent as a bonus.
  • Do not rely on a rental appraisal from the selling agent.

More first-hand cases are in what owners report.

This week's worked example

Week of 19 October 2026. A new example, rule and owner report every Monday.

A 60 m² two-bedroom flat with a standard finish on a steep block, services 12 m from the house, in Southern Adelaide: our model puts it at $220,000 turnkey ($193,500–$246,500), or $3,670 per m². At the area's median 2-bedroom bond rent of $550 a week it would return 10.3% net and pay back in 12.7 years after tax.

Rule check: A NSW complying development certificate for a detached granny flat needs a lot of at least 450 m²; under the SEPP, 450 m² is also a non-discretionary standard for a development application, so council cannot refuse a DA on lot size if the lot meets it.